2024-10-09, Signing a Grant Agreement with the CINEA agency (European Climate Infrastructure and Environment Executive Agency) for investment co-financing.

Police Seaport Authority Sp. z o. o. has signed a Grant Agreement with the CINEA (European Climate Infrastructure and Environment Executive Agency) for investment co-financing. The amount of funding granted to Police Seaport Authority Sp. z o. o. under the Grant Agreement will amount to EUR 33.4 million, i.e. 81.4% of the Project’s eligible expenses during the Project implementation period. The funding was granted under the Connecting Europe Facility (CEF) financial instrument.
The investment envisages the construction of a track and road system, along with accompanying infrastructure, including a signal building, equipped with installations and devices necessary for the operation of the facility and the railway line. It is also planned to build approximately 6 km of railway tracks and approximately 2.82 km of internal roads. The aim of the investment is to increase the accessibility of the port both from land and sea, as well as to increase transshipment efficiency. The project is expected to be completed by the first quarter of 2028.


2024-07-19, Construction of a railway junction in the Port of Police with EU funding

Police Seaport Authority Sp. z o. o. received information from the European agency CINEA (European Climate Infrastructure and Environment Executive Agency) about the positive assessment of the project “Construction of a railway junction for the Port of Police with the technical infrastructure as part of the construction of the railway line No. 437 to the Police Seaport” and granting funding under Connecting Europe Facility (CEF).
The total cost of the project is: 44,102,400.00 Euro.
Funding: 35,903,763.84 Euro.
Project duration: 38 months


2023-09-27, Signing of a contract for the construction of a heavy quay

As part of the task “Zarząd Morskiego Portu Police Sp. z.o.o. has achieved another milestone in the implementation of the study project – a contract was signed for the development of design documentation for construction works for the project entitled “Construction of a heavy wharf in the Police Port.” The contractor for this task is Antea Polska S.A.


2023-04-06, We applied for a building permit for the construction of a railway junction

As part of the task “Construction of a railway junction for the Police Port together with the necessary technical infrastructure as part of the construction of the railway line No. 437 to the Police Sea Port”, the design documentation was accepted, which allowed the Management Board of Morski Port Police Sp. z o. o. to apply for a building permit. Reaching this milestone means entering the final stage of preparation of the design documentation for the railway junction.


2023-04-06, We have selected the contractor for the feasibility study for the railway junction

Due to the high degree of advancement of design works for the task “Construction of a railway junction for the Police Port together with the necessary technical infrastructure as part of the construction of the railway line No. 437 to the Police Sea Port”, we were able to start work on the preparation of a feasibility study. We would like to inform you that the contractor of this document has been selected – Investment Realization Office KOLTECH Investor Sp. z o.o.


2022-12-20, Another important step in the implementation of study works

2022-12-20, Zarząd Morskiego Portu Police Sp. z o.o. has accepted works related to the implementation of the contract of August 29, 2022, the subject of which was the development of a program and spatial concept for the investment “Construction of a heavy quay in the Police Port”. The contractor of the concept was Lugo Projekt Hydrotechnika i Melioracje Łukasz Gontarz.

The purpose of this study was primarily:

getting to know the maximum possibility of expansion, extension of the mooring line of the Police Sea Port,
determining the maximum units that will be able to moor to the quay as a result of adjusting the depth in the Police Canal to the depth of the Świnoujście – Szczecin Fairway,
determination of navigational aspects for maximum ships,
expansion of the Police Sea Port in the context of the implementation of tasks related to the use of the potential of the Odra Waterway and the strategic goals of the Polish economy by increasing the possibility of importing raw materials of key importance for the economy by sea in accordance with the “Strategy of Grupa Azoty for 2021-2030”,
determination of the maximum potential for expansion of the berth facilities in terms of storage yards.

The most important elements covered by the study include:

construction of a heavy quay constituting an extension of the existing sea quay at the Police Sea Port,
conceptual solution of track and communication systems,
conceptual layout and design of universal storage yards.

The implementation of the program and spatial concept opens the way to commissioning design works in the field of Construction of a heavy wharf at the Port of Police.

Quay visualization:

Wizualizacja

2022-12-16, We have obtained a decision on environmental conditions for the railway junction

Zarzad Morskiego Portu Police Sp. z o.o. has obtained a decision on environmental conditions for the task ” Construction of a railway junction for the Port of Police with the necessary technical infrastructure as part of the construction of the railway line No. 437 to the Police Seaport”. Obtaining this decision allows entering the final stage of design works.

2022-10-11, Co-financing from the CINEA Agency for study works

Zarzad Morskiego Portu Police Sp. z o.o. has signed a Grant Agreement with the CINEA agency (European Climate Infrastructure and Environment Executive Agency) for co-financing of study works. The funding was granted under the Connecting Europe Facility (CEF) financial instrument.

Project title: “Facilitating sustainability of the comprehensive network by increasing the availability and efficiency of the Police Seaport”

The total cost of the project is: EUR 3,477,582.
Co-financing: EUR 1,738,791.00.

Project start: 21-07-2021.
Project completion: 20-12-2024.

The general objective of the project is to improve the accessibility and handling capacity of the Police Seaport by providing access to the railway network and improving the accessibility from the water side for seagoing vessels with a draft of up to 12 meters.

The general objective will be achieved through the following specific objectives:

increasing the competitiveness of the Seaport in Police by increasing the share in servicing international trade, especially in the Baltic Sea basin taking into account the economic development of the entire West Pomeranian Voivodeship and the simultaneous improvement of the maritime transport system,
creating access by rail to the Police Seaport,
improvement of handling efficiency and accessibility to the port from the water for seagoing vessels with a draft of up to 12 meters.

The project includes study works for two tasks:

Development of design documentation for construction works for the project “Construction of a railway junction for the Port of Police with the necessary technical infrastructure as part of the construction of the railway line No. 437 to the Police Seaport” with a feasibility study. As part of the railway junction, it is planned to connect the Port with the railway network (line 437) and the creation of railway sidings – min. 5 tracks of usable length min. 750 m.
Development of project documentation for the investment ‘Construction of a heavy quay in Police Seaport’ with a feasibility study. As part of this task, it is planned to build a heavy quay with a planned length of approximately 300 meters (this is an estimated value that will be verified at the stage of preparing the technical documentation), thanks to which the total length of the heavy quay in the port will be approx. 715 meters. The main result of this task will be the improvement of water access to the Police Seaport.